Sanwo-Olu Explains Delay in Opening Opebi-Ojota Bridge

Share
Advertisements

By Emmanuel Daniji

Lagos State Governor Babajide Sanwo-Olu has explained why the newly completed Opebi-Odoiya Alaro Link Bridge is yet to open to motorists, saying the installation of a large steel monument has delayed its immediate use.

The bridge, expected to improve movement around Opebi, Ojota and adjoining areas, was earlier scheduled to open to traffic by the end of September. However, the additional work has pushed the opening beyond the initial deadline, leaving motorists waiting for the new route to become available.

Sanwo-Olu made an unscheduled visit to the project site on Sunday, October 25, to inspect the installation and find out why the work had not been completed as planned.

During the visit, the governor said the monument was not part of the bridge’s original design. The architectural feature was introduced towards the final stage of construction, resulting in the delay.

He appealed to Lagos residents to be patient, explaining that the remaining work must be completed safely before the bridge can be opened.

According to the governor, the monument is designed to reflect the area’s history as a centre for cane weaving. The 25-metre-high steel structure will feature four hands representing the traditional craft associated with the location.

Sanwo-Olu said the installation involves a major engineering process, with approximately 300 tonnes of steel being fitted into the structure. He disclosed that three of the four steel sections had been assembled and installed, while work remained on the final section.

He put the installation work at about 80 per cent completion during the inspection and said a few more days would be required to fit the remaining steel component and complete other proposed features.

The governor acknowledged that the project had gone beyond the earlier timeline but insisted that the state would not compromise safety to meet a deadline.

He also praised officials of the Lagos State Ministry of Works and Infrastructure and the construction workers for their efforts, while urging them to speed up the remaining work.

Sanwo-Olu assured residents that the bridge would be available for use during the Christmas and New Year festive period, known as Yuletide.

Beyond easing movement, he said the bridge was expected to become a landmark that would add to Lagos’s architectural appeal and promote tourism and cultural heritage.

For motorists who have been looking forward to using the new route, the immediate concern remains when the bridge will finally open. The governor’s assurance offers hope of a festive-season opening, although the remaining installation and safety checks must first be completed.

 

 