FG targets December opening of 100km Lagos-Calabar Coastal Highway

Share
Advertisements

By Emmanuel Daniji

Advertisements

Commuters and businesses along the Lekki corridor may soon get some relief from traffic congestion as the Federal Government targets late November or early December 2026 to open completed sections of the Lagos-Calabar Coastal Highway.

The Minister of Works, Dave Umahi, disclosed this during an inspection of the project around Mayegun and Jakande Estates in Lagos.

Umahi said 100.47 kilometres of the dualised concrete carriageway had been completed, comprising 47.47 kilometres in Section 1 and 53 kilometres in Section 2.

The planned opening is expected to improve movement along the Lekki axis and provide better access to residential estates and commercial centres. However, the minister explained that the initial commissioning would exclude outstanding bridges.

He said work was still ongoing on drainage systems, solar-powered streetlights and other road facilities, which are expected to be completed before the end of December.

One of the major structures inspected was a completed flyover and U-turn bridge at Chainage 9+500. The bridge is designed to allow motorists to make U-turns through designated service lanes without disrupting traffic on the main carriageway.

According to Umahi, construction is progressing on the 20 bridges planned for Sections 1 and 2. He also disclosed that the Federal Government was concluding the bidding process for service lanes and deep drainage channels to direct stormwater into the lagoon.

The minister said the drainage facilities would be important in preventing flooding and improving access to communities along the highway, particularly during the rainy season.

He commended Hitech Construction Company Limited for its work on the project, saying the contractor had delivered more than 200 kilometres of dualised concrete carriageway within two and a half years.

Umahi also explained that the asphalt laid on the completed concrete bridge was part of the engineering design. He said it would improve the bridge’s finish and support the installation of expansion joints needed to accommodate structural movement.

Beyond the coastal highway, the minister addressed concerns over traffic congestion caused by construction work on the Lagos-Ibadan Expressway. He apologised to motorists and said he had directed that future overhead bridge installations should be carried out on Sundays, beginning from midnight, to reduce disruption.

He also gave updates on other federal road projects, including the Benin-Asaba corridor, East-West Road, Sokoto-Badagry Highway and Trans-Saharan Highway.

For residents and businesses along the Lekki corridor, the expected opening of the coastal highway sections offers the prospect of another route for daily movement. However, the extent of the relief will depend on the completion of the bridges and supporting infrastructure.

 

 