Lagos Completes Adetokunbo Ademola Road Project Two Days Ahead of Schedule
Kehinde Adeleye
The Lagos State Government has reopened the Adetokunbo Ademola section of Ozumba Mbadiwe Road in Victoria Island following 33 days of reconstruction.
Jubril Gawat, Senior Special Assistant on New Media to Governor Babajide Sanwo-Olu, announced the reopening in a post on X on Saturday.
Gawat said the reconstructed stretch, which extends to Sir Samuel Manuwa Street, was completed two days ahead of its scheduled 35-day timeline.
“Earlier today, the Lagos Office of Infrastructure and Lagos Ministry of Transportation led by the Special Adviser Infrastructure, Engr Olufemi Daramola have opened the Adetokunbo Ademola (1004) Section of the Ozumba Mbadiwe which was done all the way down to Sir Samuel Manuwa street, Victoria Island,” he said.
The governor’s aide added that further reconstruction work along the Ozumba Mbadiwe axis would resume after the 2026 festive season in 2027.
In a video accompanying his post, Gawat disclosed that the state government had also awarded the reconstruction of the Lekki-Epe section, covering the stretch from Bonny Camp to Admiralty Junction.
He said additional work was also planned around Ajah, near VGC, to improve traffic flow from the Epe T-Junction.
Gawat thanked residents for their patience during the reconstruction, assuring them that work on the remaining sections would continue after the festive period.